Wastewater Treatment Plant Expansion
Town of Kent, Connecticut

    LEA was retained by the Town's WPCA to conduct a detailed evaluation of the Townís existing wastewater treatment facility including its hydraulic capacity, organic loadings and current operational conditions. Following the detailed evaluation, LEA prepared a report which recommended additions and improvements to the plant which included increased settling and aeration capacity to handle future anticipated sewage flows and loads; increased digestion capacity to allow longer detention ties for improved solids reduction; and the installation of a sludge dewatering unit and other minor modifications to the existing plant to improve its operational efficiency.
  Following receipt of the Town's and DEP approvals, LEA prepared detailed design plans and specifications for the recommended modifications, setting forth in detail the work to be done, materials and equipment to be furnished, and the quality of workmanship required. LEA also provided the following contract administration and construction monitoring services:

• Bid review, recommendation and award.
•Shop drawing review and approval.
•Resident representation services.
•Attendance at weekly construction meetings.
•Processing of Change Orders and partial payment requests.
•Final punch list and final payment approval.
•Preparation of record (as-built) drawings.