Soil was treated to a total VOC
concentration of less than 2.0 parts per million (ppm) and replaced
on-site. Materials containing PCBs, metals and acutely hazardous
substances were shipped off-site without treatment. Over 80,000
tons of contaminated soil was treated in the on-site facility.
In addition, over 20,000 tons of material were shipped off-site
as hazardous waste. The project lasted approximately 22 months
and saved the client over $6,000,000 in Treatment costs.
|