Project Summary:
The central heating plant for the facility was in the process of being decommissioned. Several buildings which were
to remain occupied required a stand alone source of heating steam. BJFW consulting engineers presented several options
and after careful review, the client selected a factory fabricated packaged boiler system. The 250HP fire tube boiler system
was delivered to the site and consisted of:
• a chemical feed system, • makeup air heater,
• boiler feedwater system • ventilation system,
• water softener • power distribution system and controls • blowdown system,
Final connections for gas, water, sanitary, and electrical were made by the installing contractor.
|
|